Table 1. Project Priority Evaluation Form.
Must objectives
Must meet if impacts
Proposal
1
Proposal
2
Proposal
3
Proposal
4
Be safe, legal and comply with university policies
Y = yes
N = no
Earn at least $500
Y = yes
N = no
Can be completed within 9 weeks
Y = yes
N = no
Opportunity to learn project management
Y = yes
N = no
Want objectives
Relative Importance 1 – 100
Single project impact definitions
Weighted Score
Weighted Score
Weighted Score
Weighted Score
Earning potential
90
0: 500–750
1: 750–1500
2: >$1500
3: >$2000
Fun
30
0 = Non
1 = Some fun
2 = Much fun
Increase awareness of the charity
30
0 = No potential
1 = Low potential
2 = High potential
Resume worthy
40
0 = No potential
1 = Low potential
2 = High potential
Be featured on
local TV news
40
0 = No potential
1 = Low potential
2 = High potential
Total weighted score
Priority
Table 2. Shoreline Stadium Project.
ID
Activity
Duration
Predecessor(s)
1
Baseball Stadium
2
Clear stadium site
70 days
–
3
Demolish building
30 days
2
4
Set up construction site
70 days
3
5
Drive support piling
120 days
4
6
Pour lower concrete bowl
120 days
5
7
Pour main concourse
120 days
6
8
Install playing field
90 days
6
9
Construct upper steel bowl
120 days
6
10
Install seats
140 days
9
11
Build luxury boxes
90 days
9
12
Install jumbotron
30 days
9
13
Stadium infrastructure
120 days
9
14
Construct steel canopy
75 days
10
15
Light installation
30 days
10
16
Build roof supports
90 days
4
17
Construct roof
180 days
16
18
Install roof tracks
90 days
14
19
Install roof
90 days
17,18
20
Inspection
20 days
8,11,13,15,19